Tobin Bridge/Chelsea Curves Rehabilitation Project Update
Construction overview: August 11 - August 24, 2019
Traffic Impacts
• Route 1 Northbound: Approaching the Tobin Bridge from Boston, the workzone begins in the right lane. 2 of 3 travel lanes will be open during daytime hours (5 a.m. – 10 p.m.) and at least 1 travel lane will be open during overnight hours (10 p.m. – 5 a.m.).
• Route 1 Southbound: Approaching the Chelsea Curves from the North Shore, the workzone begins in the right lane at the Carter Street off-ramp. Just beyond the Carter Street on-ramp, the travel lanes shift to the right. 2 of 3 travel lanes will be open during daytime hours (5 a.m. – 10 p.m.) and at least 1 travel lane will be open during overnight hours (10 p.m. – 5 a.m.).
• Ramps: As of Monday, July 15, the Fourth Street Off-ramp will be closed for 2-3 months.
• Local Streets: Orange Street under Route 1 will close temporarily on Saturday, August 17, from 7 a.m. to 7 p.m. From Monday, August 19 to Friday, August 23, Spruce Street between Sixth Street and Everett Ave will be CLOSED overnight from 7 p.m. to 6 a.m. for bridge work with traffic detoured one block to Arlington Street. The Spruce Street temporary reconfiguration and Carter Street workzone will remain in place until Fall 2019.
Work Hours
• Most work will occur in during daytime working hours (6 a.m.–2 p.m.) on weekdays. Some work will take place during afternoon (2 p.m. – 7 p.m) and overnight hours (9 p.m. – 5 a.m.) and on Saturdays (6 a.m. – 2 p.m). Overnight work on the Tobin Bridge will occur on Friday, August 18 (9 p.m. – 5 a.m.).