Tobin Bridge/Chelsea Curves Rehabilitation Project Update

Construction Look-Ahead: September 05 – September 18, 2021 


This is a brief overview of construction operations and traffic impacts for the Tobin Bridge/Chelsea Curves Rehabilitation Project. MassDOT will provide additional notices as needed for high-impact work, temporary ramp and street closures, and changes to traffic configurations beyond those described below. 

ROUTE 1 TRAFFIC IMPACTS ROUTE 1 NORTHBOUND: Approaching the Tobin Bridge from Boston. All 3 travel lanes will be open during daytime hours (5 a.m.– 9 p.m.). 

ROUTE 1 SOUTHBOUND: Approaching the Chelsea Curves from the North Shore. All 3 travel lanes are open during the daytime hours (5 a.m. - 9 p.m.). 

LOCAL STREET CLOSURES ARLINGTON STREET: During the week of 9/6, Arlington Street will be closed Tuesday through Friday during the daytime (7 a.m. – 3 p.m). SPRUCE STREET: During the week of 9/6, Spruce Street will experience a single lane closure from Tuesday through Friday during the daytime (7 a.m. – 3 p.m.).